After creating some projects with subprojects and some activities, In the planning function I started to change the position to fit the real order I want projects to be planned.
I had 1 master project (my program) with 3 projects under it (there's more to add but I got stuck at this point and it's enough to explain the issue). and some activities planned under some projects.
As I moved project 1.3 above project 1.2 (intentionally to change the wbs) it changed the wbs of projects and activities correctly but this resulted in a very odd positioning, as shown on the attachment.
I guess you're in V4.1 or previous version.
This is an issue fixed in V4.2
You're right... I'm still using v4.1.2.
I will run the update and see what happens (and give you some feedback).
Thanks 😀
Problem solved updating to v4.2.1