Hello, perhapse you may help us with a problem with the calendars. We have the default-calendar with the holidays for all resources together and then everyone has his/her own calendar with his/her own holidays. But when we view projects in the planning or the monthly planning report there you can only see the default-calendar in the background. So you can’t see the personal holidays of each resource.
For example, one resource ‚MH‘ (Mr. Heiligmann) is on holidy from 22th - 26th of May. But it isn’t shown on the planning and the reports.
Thanks for your help.
We have the default-calendar with the holidays for all resources together and then everyone has his/her own calendar with his/her own holidays
This is not the good way to manage off days on ProjeQtOr.
This is way to do with MS-Project (single project management), not with PROJEQTOR.
Read user manual and look at Administrative projects.