Hello,
I need to create a milestone 13 days after the beginning of an activity, but whenever I try to make a dependence start-start, I keep getting a planning with a dependence end-start.
Can you help me on this issue, please?
Regards,
MCanuto
Click on the dependency line to change the dependency properties.
Your milestone must be a floatng milstone, not a fixed one.
It is a floating milestone.
Can you try and re-plan your project.
I met some cases when changing dependency type required 2 planning to be correctly taken into account.
It still didn't work.
I realised that the milestone was scheduled at the begin of the last sub activity of "Non-Regression Tests".
I made it depend "start-start" on the first sub activity of "Non-Regression Tests", and it worked. But it's not really what I wanted to do, because this couldn't change in time.
It seems the issue is related to the fact that the precedent activity contains sub-activities.
I'm not sure if what I wrote is clear....
Hi,
This seem to be an issue.
Ticket #5406 recorded.