Hello,
we have noticed what seems to be an anomaly.
We have a full schedule calculation task scheduled each morning and we can be required to perform manual planning during the day.It turns out that the result is different without change on our part, we observed delays of 3 weeks on certain tasks according to the 2 modes of execution.
For manual mode, we use the admin account, all projects and the start day is the current date. which is in principle equivalent to the configuration of the cron job.
Could you explain this difference?
Thanks for your help.
Hello,
If your CRON has been running for a while. Test to stop and restart it. It is possible that it is still running on an old version of the code.
Also check that you have not enabled the use of sucapacity during manual planning and that you have hidden the option without disabled it.