Planning Problem
 
Notifications
Clear all

Planning Problem

5 Posts
2 Users
0 Reactions
3,072 Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#2813]

Hi

Today, I plan a task with a work but I was surprised about the planning, this task was planned for last friday. How is it possible if the task is created today? Why the planified date is 11Dic2015?

I changed the requested date to see the impact but nothing is done, what is the goal of the requested date field?

Thanks


 
Posted : 14 Dec 2015 12H57
(@babynus)
Posts: 14952
Member Admin
 

There in no impossibility to plan a task before current day.
Requested date has no effect on planning : it is only informative.


 
Posted : 14 Dec 2015 22H52
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

There in no impossibility to plan a task before current day.

But if I'm creating the task today, I didn't work on this task last friday so the task is late before begin it. :blush:

I don't understand in which case is useful plan a task before current day?


 
Posted : 15 Dec 2015 11H16
(@babynus)
Posts: 14952
Member Admin
 

If you define a task that can have been worked on by resource during current week, it may be usefull to plann it fro real start day (and not from current day) if you know that resource has not entere d real work yet.
Now it is just a possibility.
If you ru pllanning calculation with stating date ) today, you won't have this behavior.


 
Posted : 15 Dec 2015 20H52
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Thanks for the clarification.

If I define a starting date with ASAP planification mode, the starting date is just an indication to plan (ie at least the task should be begin at the starting date, but it is possible to plan after depends of priority and disponibility of ressources).


 
Posted : 16 Dec 2015 11H58