Hello,
This issue is a little related to my previous subject about pool resources at 100% in several pools. We have begun to use it and we've faced a big issue with closed pools. It appears that the check function which verify that a resource is not in pools at more than 100% consider the closed pools but not closed resources into pools. This requires to delete pools and not to close them... What would be the use of closing a pool?
Maxime
Posté : 25 Mar AM 10:033
Issue recorded as Ticket #4557
Posté : 25 Mar PM 18:033