Forum

Scale problem in th...
 
Notifications
Retirer tout

Scale problem in the Gantt Planning

2 Posts
2 Utilisateurs
0 Reactions
1,102 Vu
(@c-munoz)
Posts: 7
Active Member
Début du sujet
 
[#8964]

Hello,
I'm using the 10.3.6 version. In the Gantt Planning, I have detected an issue. When I select the weekly scale, I see the daily scale when I right click on certain activities or I see the weekly scale but out of sync with the timeline above. This is an issue because I cannot properly visualize the real and planified work. (See the screenshots below to understand my problem).  

Thank you,
Best regards,
 


 
Posté : 7 Juil PM 17:077
(@babynus)
Posts: 14952
Membre Admin
 

Could you please show detail (all dates) of activity with issue.


 
Posté : 10 Juil AM 11:077
Share:
Retour en haut