In the incoming windows, the value in "impact work" seem to be rounded in days
if i enter 40 hours, when we hit save the value is changing to 37,5 hours.
Expected behavior: keep efforts in hours as entered.
Regards
Hello,
Please specify on which screen you are.
In your global parameter, have you your unit for workload on hours ?
Indeed there is an issue, we have created the tiket # 4507.
It will be patched on version 8.3.5.
In the meantime, just change the type to decimal(12,5) of impactWork on the DB for table Deliverable.