Hello, I have a project blocked for all fields, withn "en cours" status. 2 activities of this project blocked in "en cours" status without any other choice in the dropdown list.
Workflow is OK, I have admin privileges.
Probably issues in time sheets or work in tickets.
Thanks for helping!
Sorry but I really don't understand your "issue".
"project blocked" : what is it ?
Please explain.
Maybe some screen shots...
I have no possibility to change any project information (All fields in grey, status "en cours").
Project's activities in "en cours" status, unable to change status. Best regards
Check the flag "idle", it may be checked whatever the status (may be checked from parent if user has "force close" specific right)
I will close all tickets linked to activities, then I will try to close activities if possible and see effects on the project where all fiels are in grey.
Thanks
Possibly it is just acces right.
Your profile may just give you read access to actitivities on some projects.
Thanks! It was the issue. Best regards