Hi,

On projeqtor 11.4.0, in a "Time & Materials" project, a resource has assigned work on an activity and he is the only assigned resource. The activity has then been changed to state "closed". In gantt view "planning by resource", the closed date is 09/10/2024. In standard planning screen, the closed date is 26/09/2024. The project has been recalculated before and after without showing any change. Why is there two different "closed date" ?

Thanks a lot 
F.


 
Posté : 02/10/2024 6:19 pm
(@babynus)
Posts: 14952
Membre Admin
 

Is there any real work entered on the Activity ?


 
Posté : 10/10/2024 6:37 pm
(@fsobel)
Posts: 20
Eminent Member
Début du sujet
 

Yes, there is.
I check today and now both views are identical. So I close the subject on my side until further new notice of such effect.
Thanks a lot.
F.


 
Posté : 10/10/2024 6:55 pm