Hello,
I'm having a issue with the "whole team assignement" to a reunion.
If a ressource is "Closed" and even if he doesn't belong to the project team anymore, when I choose to assign whole the project team to a reunion, the ressource is still assigned.
Is it normal? What can I do to prevent it?
Thank you for your help.
Hello,
Indeed, the button "assign whole project team" doesn't handle closed ressources.
Ticket #4020 created to fix error.
thank you.
Hi,
Thank you for your answer.
I've realised that there's another issue concerning the assigned work. When I delete assignement to a meeting, the assigned work doesn't change..
It's probably not related, but since...
Can you check it too?
Than you
hello,
I've realised that there's another issue concerning the assigned work. When I delete assignement to a meeting, the assigned work doesn't change..
indeed there is an issue, ticket#4024 created.