I'm having a issue with the "whole team assignement" to a reunion.

If a ressource is "Closed" and even if he doesn't belong to the project team anymore, when I choose to assign whole the project team to a reunion, the ressource is still assigned.

Is it normal? What can I do to prevent it?

Thank you for your help.


 
Posté : 22 Mai AM 00:055
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

Indeed, the button "assign whole project team" doesn't handle closed ressources.
Ticket #4020 created to fix error.

thank you.


 
Posté : 22 Mai PM 15:055
(@mcanuto)
Posts: 183
Active Member
Début du sujet
 

Hi,

Thank you for your answer.

I've realised that there's another issue concerning the assigned work. When I delete assignement to a meeting, the assigned work doesn't change..

It's probably not related, but since...

Can you check it too?

Than you


 
Posté : 22 Mai PM 17:055
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

hello,

I've realised that there's another issue concerning the assigned work. When I delete assignement to a meeting, the assigned work doesn't change..

indeed there is an issue, ticket#4024 created.


 