Dear team,

I have an old task that I can't close, due to the fact that Projeqtor is reporting left work that doesn't exist (or that I can't find).
The task has no subtask :
 

Do you have any idea how to solve that issue ?

Thanks !


 
Posté : 3 Fév PM 13:022
(@louisc)
Posts: 58
Active Member
Début du sujet
 

Hi again,

I have an other task with similar problem. Once again, only 1 ressource assigned to the task, no more left work on the ressource. But this time, we can see there is real work reported but not for the assigned ressource... 


 
Posté : 3 Fév PM 16:022
(@louisc)
Posts: 58
Active Member
Début du sujet
 

Hello,

I finally found where was the left work. It was in meetings that were not closed.
Not a bug, I close the issue.


 
Posté : 3 Fév PM 20:022