Hello,
i use template report to show projet and linked activities (using linked element to get activities).
In my project, i link 2 activities (#3 and #4) link here :
Each activity is planned as visible here :
I use template report (see attachement) to get project data and linked activities datas (i use every fileds for activity in my test template).
While generating report, i get no data for initialDueDate and ActualDueDate for activities (see attachement).
Any idea ?
Best regards,
I understand but why refInitialDueDate is empty ?
Regards
Because Activity does not have initialDueDate
It has ValidatedEndDate, PlannedEndDate, .... but not "dueDate" which are defined on Action, Risk, ...