validate work not calculate on project when it is calculate with orders

2 Posts
2 Users
0 Reactions
1,371 Views
(@pipobru)
Posts: 180
Active Member
Topic starter
 
[#8415]

Hello, i have this strange comportement with 10.0.2 version.

  • Create a new project
  • check the option for calculated validated time on order
  • add new order (with charge validate)

And now when you read validated time in the project the value is 0.
For solve that:

  • Create new activity with charge validate
  • uncheck the option in the project ==> Validate time is now correct (same as activity)
  • Re check the option for calculate validated time with orders.

And now the calcul is good.

Thanks for this tools it is a very very good tools !


 
Posted : 17 Aug 2022 14H37
(@babynus)
Posts: 14952
Member Admin
 

Ticket #6404 recorded


 
Posted : 17 Aug 2022 20H45