Hi all,
The issue you might have:
- On project start we often know expense positions by naming them, but not the ballpoint / estimated amount. Hence we have to enter no value or even '0' in the amount field.
- ProjeQtOr is checking this entry and rejecting value '0' in the amount field
😳
My proposed solution:
Enter '0,001' in the amount field. As this field will be rounded up, you have value '0' in your field. 🙂
I hope you like this workaround.
Klaus