We have used on some of our projects a technique called Critical Chain Project Management. CCPM has anyone any experience using the concept of feeding and chain buffers with Projeqtor. We link MS project to a program called Concerto .
Hello,
Projeqtor is using Critical chain project management in its critical path calculation.
Because we take into account the availability of resources in the planning calculation.
Thank you for not advertising projeqtor concurrents on the forum.