Change the unit of work/real work allocation

3 Posts
2 Users
0 Reactions
4,429 Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#3780]

Hi,

My general settins is set to hours for both parameters (work/real work allocation).

What's happen on my actual data (work on activities and on real work allocation) if I change both parameters to days ? Is it converted to day?


 
Posted : 24 Oct 2016 18H16
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Nothing happens to your data.
Data is always stored in days.
When you select to display/input in hours, a conversion is applied.


 
Posted : 24 Oct 2016 18H27
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Thanks for your explication.


 
Posted : 25 Oct 2016 15H50