dates in projeqtor tool

4 Posts
3 Users
0 Reactions
1,831 Views
(@jagriti-pandey)
Posts: 4
Active Member
Topic starter
 
[#7652]

There are so many dates in projeqtor.
could u please explain following dates with good example 
start date
done date
creation date
validated start date
validated end date
real start date
real end date
requested end date
requested start date
planned start date
planned due date

 


 
Posted : 29 Jul 2021 12H34
(@babynus)
Posts: 14952
Member Admin
 

Have a look at the beautiful user manual that in provided with the application and directly reachable through F1 with contextual access.
Or in other word : RTFM


 
Posted : 30 Jul 2021 13H36
(@jagriti-pandey)
Posts: 4
Active Member
Topic starter
 

I initially read user manual for dates but In the user manual, dates are not explained clearly. could you please explain again here with good example.

Already messed up with so many dates.

what is difference b/w start date vs validated start date vs planned start date??
Similarly diff b/w planned due date vs planned end date or done date ??


 
Posted : 30 Jul 2021 14H11
(@marylene)
Posts: 592
Member Admin
 

It is true that one or two details are missing from the manual and the next version will be a little more explicit thanks to you.

To keep it short and simple:

Requested: customer's request
no impact on planning EXCEPT if it is the one and only constraint entered.

Validated: What you plan
Used for certain planning modes and to compare the drifts with the dates planned by the software

Planned: What the software calculates for you
You do not have direct control over these dates. The calculation takes into account absolutely all your constraints to calculate a planning with total care.

Real: What you achieve
You fill in the real work on your timesheet. It's done.

The creation date is the date you create the item
The in progress date is when you start to work on the element.
The end date is when you're done, no more left work to do.
The closing date is when you close your item.
The modification date is the last date on which the item was modified.

I don't think we can be any clearer.
Now if you have a hard time with writing, we have great training. Do not hesitate to request a quote with our contact form.


 
Posted : 30 Jul 2021 14H43