Difference date between planning / ressource planning

2 Posts
2 Users
0 Reactions
3,572 Views
DEDIEU
(@jcde)
Posts: 104
Active Member
Topic starter
 
[#984]

Hi,

There is a difference logic between the display for planning and planning by resource.
In the planning view, the Gantt displays dates validated when there is no dates planned.
While the planning for each resource, if there is no dates planned, nothing is drawn. Why the logic of the planning view is not used in the planning view by resource?

Thanks


 
Posted : 25 Feb 2013 20H28
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

The difference come from different point of view :
=> on resource planning, you see dates correponding to planning for the resource.
=> on planning, you see dates corresponding to the activity.

Let's concider an exemple :
For task1, Res1 is planned from D1 to D2
For task2, Res2 is planned from D3 (D1<D3<D2) to D4 (D2<D4)

D1___D3___D2___D4

On planning you'll see only one bar from D1 to D4

D1_____________D4

On Resource planning you'll see 2 bars, one for Res1 from D1 to D2, one for Res2 from D3 to D4

D1________D2
     D3________D4

Now, on resource assignment, you never define "validated date" : that's why it cannot be displayed at resource level. Only planned dates can be displayed.


 
Posted : 26 Feb 2013 17H02