Following tasks could not be completely planned

4 Posts
2 Users
0 Reactions
2,528 Views
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 
[#4377]

Hello all,

I have a problem if I assign ressources to Meetings. If I run the planning I always get the follwing pop-up Following tasks could not be completely planned
See also the attached pic.
If I do this with an activity on the same ressources it is no problem and the planning runs fine. Also on the same day there is no other activity, etc for that ressources
So I do not know what I am missing.

Any help is very much appreciated 🙂


 
Posted : 23 May 2017 19H39
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

Check reports in category "planning" : some will show you planned work day by day for the resource, so you may find some unexpected planned work for the resource.


 
Posted : 23 May 2017 23H01
(@chris_1784997064)
Posts: 50
Active Member
Topic starter
 

ok I found the issue.
I have the following structure:

Main project (administrative)
|- Subproject (administrative)
| - sub-sub-project (internal project)

I assigned my ressources to the main project, but with 0% rate.
So even if I assigned 100% to the internal sub-sub-project , it seems to be that the available rate follows that of the main project, which is zero.

If I now set the rate in the main project to 100% it is ok...
But it is also ok if I remove my ressources from the main project, so that they are only assigned to the sub-sub-project.

So long explanation but the question is now, if this behaviour is intentionally and is as follows:

Assume that
the ressource is assigned to the main project with e.g. to rate 100%, then to the sub-project 50%, then to the sub-sub-project also to 50% --> Is the maximum rate of the sub-subproject now effective 25%?
Did I get this right?

Thanky you very much


 
Posted : 25 May 2017 0H26
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

Not exactly.
Allocation rates do not multiplicate.
They are limits.
So the smallest will be the constraint.
A1 => 100%
A1.1 => 50%
A1.1.1 => 50%
then limit on A1.1.1 is 50%
A1 => 50%
A1.1 => 100%
A1.1.1 => 100%
then limit on A1.1.1 is also 50%


 
Posted : 25 May 2017 19H43