Bonjour,
Est-ce que cet outil gère les congés (payés, non payés, maladie) ?
Si oui, comment gérer ça ? Si non, Auriez-vous une idée pour contourner ça ?
Merci.
PLEASE POST IN ENGLISH.
Of days (holidays, sickness, training) are managed through "Administrative" projects.
Have a look at it in the Online manual.
I created an administrative project but i didn't know how to assign off days to resources.
Thank you.
You just have to enter Real Work (thought real work allocation screen) for administrative projects.
You don't need to define assignment, nor affectations (this is the interest of administrative projects).
Hello, i do not find the button Real Work Allocation in menu...
How to setup different type of days off to be selected by users in that specific administrative project?
Real Work Allocation
It is now called "Timesheet"
("Imputations" in french)
You have to define one Administrative project.
Then you add as many activities on this project as you wish : every user will see these lines in their Timesheet
(no need to create allocations to project, nor assignment to activities)
NB : V7.4 will provide a new way to enter this kind of work, in a "calendar like" view.
Hi
Ok understood, but i would like to create a workflow about days off (manager approval, HR approval, etc..). So how to connect a workflow as you said to use timesheet only where i do not find worflow feature?
Thanks
And i would like to add that People would be able to input days off only if It is approved.
Waiting for your help
Hi,
It is subject of contribution from Tabary that we will include on V8.0
Hi, ok when do you plan to release V8?
mid-april