Hello,
When I create an activity, I can put "start date requested" and "start date validated", the same for end date.
but how can i put the planned date ?
I thought it was on the planning of the ressource affected to the activity but I didn't find anything.
Can someone help me ?
Thanks
Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2
Yes, planned dates are defined according to assigned work defined for resources to tasks.
For the first draft of project plan, you can use validated dates or requested dates to defined planned dates.
Thanks for help, but I don't understand all you tell me 🙁
I've assigned work to a ressource for a specific taks but the field "Planned" is still empty (see image below)
Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2
Are you executing the process to calculate planning?
The process can be started in the Gantt chart.
Fine : it works.
I didn't know this functionnality.
Thanks
Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2
It's my fault!
I rewrite the user guide.
Next version will contain this information.