Not able to change number of hours per day in Global Paramaeters

8 Posts
2 Users
0 Reactions
7,056 Views
(@iconic)
Posts: 280
Active Member
Topic starter
 
[#4579]

I am trying to change the number of hours per day in Global Parameters, however it is greyed out and I can't make any change to this.
I have read the online manual and have changed the Daily work hours, however the number of hours per day : in Global Parameters remains as 22.5.

How can I change this to make it 12 hours for number of hours per day : in Global Parameters.


 
Posted : 13 Aug 2017 4H30
(@iconic)
Posts: 280
Active Member
Topic starter
 

Also, is there a way to make individual staff (resources) work a specific number of hours per day. For example, I have my full time staff member who works 12 hours per day, but my part time staff member who works only 4 hours per day.

Is there a way when planning, that I can plan based on the number of hours they work per day?


 
Posted : 13 Aug 2017 4H32
(@babynus)
Posts: 14952
Member Admin
 

You cannot change hours par day if :
- you defined real work format as hours
- some real work exists.
This is because ProjeQtOr always stores day.
So display of hours is always a converted value.
If some resource entered 12 hours for à 12 hours per day value, 1 days is stored.
So if you change hours per day to 10, when resource gets back, he sees 10 hours although he entered 12 hours.

The only "realistic" way change hours per day is to remove all existing real work...

Now there is a workaround :
- change unit for real work to days, save
- refresh parameters screen : now you can change hours per days...
- when it's done, change back unit for real work
But you must be aware that you'll face previously pointed out issue (resource that entered 12 will now see 10)


 
Posted : 13 Aug 2017 15H48
(@babynus)
Posts: 14952
Member Admin
 

For example, I have my full time staff member who works 12 hours per day, but my part time staff member who works only 4 hours per day.

This is easy : your part time resources have capacity of 0.33 (well 0.333333333... in fact).
Another way to deal with resources working different times, is to define work days as 10 hours per day.
Then, resoures working 12 hours per day have capacity of 1.2, resources working 4 hours per day have capacity of 0.4


 
Posted : 13 Aug 2017 15H52
(@iconic)
Posts: 280
Active Member
Topic starter
 

This works well and I can do that, but where do I define the hours for each resource. I cant seem to this part. Is it in resources? It is it Values? Is it in global parameters?


 
Posted : 14 Aug 2017 8H29
(@babynus)
Posts: 14952
Member Admin
 

Hours for each resource will be defined as Capacity on the Resource screen.
Capacity is 1 for 1 full day per day.
If you defined 12 hours per day :
- capacity 1 works 12 hours per day
- capacity 0.5 works 6 hours per day
- capacity 0.25 works 3 hours per day
and so on...


 
Posted : 14 Aug 2017 11H05
(@iconic)
Posts: 280
Active Member
Topic starter
 

Thank you for that update. So in resources section 100% means 1 day of 12 hours (if number of hours per day is 12 hours).

So when I assign at task in Assignment to a Resource and I put 50% as the rate, if their resource section is 100% but the activity in assignment is 50% rate, that means that activity will allocate half a days work for the resource.

Would that be correct?


 
Posted : 15 Sep 2017 13H56
(@babynus)
Posts: 14952
Member Admin
 

So in resources section 100% means 1 day of 12 hours

Yes, except that "capacity" of resource is not in percent but in FTE (full time equivalent), so 1 day per day is capacity 1.

So when I assign at task in Assignment to a Resource and I put 50% as the rate, if their resource section is 100% but the activity in assignment is 50% rate, that means that activity will allocate half a days work for the resource.

Yes, half a day per day.


 
Posted : 15 Sep 2017 17H53