Hello,
How to force the planned start date to be calculed ? In fact, in my project I have a planned start date for a parent activity : 03/04/2014 while all validated start date are > 05/05/2014.
I calculated several times the planning via the button without succed.
The planned start date should be 05/05/2014
Thanks
Do you have some work defined for your tasks ?
If not, what is the planning mode )
For defaut planning mode (as soon as possible) you need to have work defoined to get some result.
Otherwise, you need to change planning mode (fixed duration) to get things calculated
hello,
it's solved now by affecting ressources to the parent activities.