Hello,
I want to be able to define an action just 10 days before a milestone. If the load is too large it would have to be 11 days, pulse 12 etc. But I don't wish it to be placed as soon as possible.
I didn't found a little elegant solution : A negative ejours number by defining the action after the milestone.
Example: convening a meeting which must be carried out 10 days before.
Thank you for your help


 
Posted : 23 Feb 2019 12H45
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

Keep planning mode as "asap", but define a dependency "end-end" from milestone to activity.


 
Posted : 24 Feb 2019 21H01
(@jb21)
Posts: 6
Active Member
Topic starter
 

Thanks for your reply,
I did not understand... As can be seen on the attached catch, the activity is programed as soon as possible.

Thanks in advance for your answer,


 
Posted : 25 Feb 2019 17H39
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

Take care of the way you define the dependency.
For end-to-end dependency, the predecessor (the one you drag from) is calculated, then the successor (the one you drag to) is calculated backward


 
Posted : 25 Feb 2019 17H42