Hello,
I am looking how to know the progress based on validate date vs real progress in %.
Somenoe how toknow?
Example: At september 5, I planned(validated dates) to earned 25%(project progress) but in real work I just gained 20% ?. How can i get that?
Thanks
Evelio
You don't have this information as initial planning detail is not stored.
So you cannot estimate expected progress art a given date.
What you get is Expected progress with current work VS Real Progress.