Report to include all(Validates,Planned and Real dates) for a project

10 Posts
3 Users
0 Reactions
3,457 Views
(@navver1990)
Posts: 49
Active Member
Topic starter
 
[#7632]

Hello all,

Is there any report which can show all the details(Validated,Planned and real dates)for project and 
its activities.

Thanks,
Naveen


 
Posted : 16 Jul 2021 14H56
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

The Gantt Chart.

Note that Gantt chart as Report will show same columns as the ons you select on Gantt chart screen


 
Posted : 16 Jul 2021 16H45
(@alain-fourastie)
Posts: 366
Active Member Moderator
 

Of course yes !
Have a look into report / planning.
or you can use filters on lists of projects with your values requested.
We also develop dashboards and reports on demand....


 
Posted : 16 Jul 2021 16H52
(@navver1990)
Posts: 49
Active Member
Topic starter
 

Hello,

Please find the attached Gantt report generated by me.I have selected all the field but still in that validated(baseline) start and end date is missing.How to put that in report.

Thanks,
Naveen 


 
Posted : 17 Jul 2021 7H58
(@navver1990)
Posts: 49
Active Member
Topic starter
 

How you develop reports on demand


 
Posted : 17 Jul 2021 8H22
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

I think position of slider is also taken into account.
It means of you seen only 5 colomns on Gantt Chart, only these 5 visibile columns will be exported or report.


 
Posted : 19 Jul 2021 12H54
(@navver1990)
Posts: 49
Active Member
Topic starter
 

That is Okay,but my question is regarding the inclusion of baseline start and end date in the report apart from planned start and end date.


 
Posted : 20 Jul 2021 8H07
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You may mean "'validated start date" and "validated end date", that you can add on Gantt table (use columns selector button)


 
Posted : 20 Jul 2021 14H06
(@navver1990)
Posts: 49
Active Member
Topic starter
 

Hello,
In the Column selector table in the Gantt chart,there is nothing for validated start and end date ,only selection is there for planned start and end date.How to include now those dates for my reports generation.


 
Posted : 22 Jul 2021 10H17
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes, you're right.
IOn fact what you try to do is not possible.

Only option : save baseline and export PDF from Gantt Screen with baseline


 
Posted : 22 Jul 2021 12H04