Hi

I didn't find a report that shows all tasks which were terminated before the planified date, is it exist?

Thanks


 
Posted : 16 Dec 2015 19H09
babynus
(@babynus)
Posts: 14956
Main Contributor Admin
 

This report simply does not exist.


 
Posted : 17 Dec 2015 13H10
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

Have you plan this evolution on your road map or it is not necesary in your opinion?


 
Posted : 17 Dec 2015 13H23
babynus
(@babynus)
Posts: 14956
Main Contributor Admin
 

I really don't see the need.
This could be a specific report that you'll design on your own or have designed.


 
Posted : 17 Dec 2015 13H26
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 

In my opinion, the need is show all projects which were bad plan at work estimation level. I think some PM need to have this information.

But no problem, it was just a question.

Thanks for answer.


 