Show "extra" days in projects

2 Posts
2 Users
0 Reactions
2,708 Views
 Iga
(@igabiva)
Posts: 1
New Member
Topic starter
 
[#3318]

Hi all,
noob question I guess, but so far I cannot see when a project is delayed in planning view :blush: .
Do progress bar can switch from green to red when end date has passed ? (green before end date and red after)
So I can see right away how many days I underestimated ???

Thanks !


 
Posted : 21 Apr 2016 20H49
babynus
(@babynus)
Posts: 14956
Main Contributor Admin
 

Do progress bar can switch from green to red when end date has passed ?

Yes : define target end date in Validated end date. If planned end date passes over Validated end date, task is red.

So I can see right away how many days I underestimated ???

Define validated cost. Then margin will indicate difference between validated and reassessed work. Negative margin is underestimated work, and so displayed in red.


 
Posted : 23 Apr 2016 0H07