Hi all,
noob question I guess, but so far I cannot see when a project is delayed in planning view :blush: .
Do progress bar can switch from green to red when end date has passed ? (green before end date and red after)
So I can see right away how many days I underestimated ???
Thanks !
Do progress bar can switch from green to red when end date has passed ?
Yes : define target end date in Validated end date. If planned end date passes over Validated end date, task is red.
So I can see right away how many days I underestimated ???
Define validated cost. Then margin will indicate difference between validated and reassessed work. Negative margin is underestimated work, and so displayed in red.