Hello,My problem when I have activities <1 day, the management of projeqtor does not seem correct to me.
Indeed if I have 2 activities of 0.5 days I would expect these 2 activities to end at the end of one day, but under projeqtor ends during the second day.
Do you have a solution?
Thanks,
Florian
This happens if you add dependency between tasks.
Defautl dependency mode is "strict", meaning that if predecessor end day D, successor will start at D+1
You can change this behavior in global parameters.