Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi again,
Maybe it's a strange question but is there a way to see only the selected project (the one selected on the "project selector" input) into the timesheet ?
It seems that this selector has no effect, and all projects where you have affected tasks are displayed ...
Thanks 🙂
which Projects and Projects items you see is dependant from the rights you have. if you have ...+ rights on any item (for example Updater+ on Activities) then you see all the Projects.items, because ...+ has the the right to Access items in all Projects. without the plus you see only your Project items.
There is no reason to use the selector since all the projects and so on activities to which the resource is assigned to are automatically displayed into this list.
You can not select just one project in this screen, it is not made for this use. Thus the resource sees at a glance where it must impute its work among lines of its projects and activities.
Well there is 'always' a reason for customer point of view ^^.
When you have such more thant 20 projects opened with more than 20 assigned tasks on each of them, it's obviously FASTER to be able to select the project you want to fill the timesheet and it's obviously a way not to make error on task with a quick 'fill-in'. 😉
But nevermind, I've got my answer 🙂
Thanks for your answer
There is a real reason why project selector filter does not apply on Timesheep.
When resource enters work on timesheet, he need to see all what is already entered to be able to "fill in" the week data.
It we hide some projects, all data won't be displayed and resource may easily enter more than 1 day per day without noticing it.