Hello,
When I created a new project but I saw that activities was not recorded in planning by resource but the normal planning is correct. How can I correct that ?
Thank you for your futur answer
Please show some screenshots
Hi,
You just did not "calculate" the planning (use Gear button on planning screen).
I saw this as there is no planned date (so nothing to display for resources)
NB : you have issue with currency character. You may change it on Global parameters.
Thank you very much for your quick returns