[SOLVED] How is define the critical path in projeqtor 7.0.1

5 Posts
2 Users
0 Reactions
4,351 Views
(@vlepetit)
Posts: 15
Active Member
Topic starter
 
[#5057]

Hi,

How the critical path is calculate ?

Does we setup something particular to include task in critical path ?

Regards,
vlepetit


 
Posted : 30 Mar 2018 16H23
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Once planning is calculate, a quick reverse planning is done, from end to start (taking only calculated duration of tasks), to determine latest start and end dates.
When planned dates are equal to latest dates, activity is on the critical path.

This means that if on task included in the critical path extends, whole projects extends of same duration.


 
Posted : 30 Mar 2018 16H58
(@vlepetit)
Posts: 15
Active Member
Topic starter
 

Ok,

but when there are none contiguous task in critical path, there is problem no ?
like when the planned end date of the first task is before the planned begin date of the next task, the critical path seem to not be display.

example in your projeqtor demo :
the task with wbs : 99.2.1 is the first task of an task chain. this task is none contiguous with the next task (wbs: 99.3.1) and it's not in critical path. but the task (wbs: 99.3.1) that is contiguous with the next step task, is in critical path.

It's normal ?

Regards
vlepetit


 
Posted : 30 Mar 2018 17H26
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Yes, it's normal.

Concider that task 9.2.1 extends of 1 day : end date of project does not change.
So this task is not on critical path

Now, extend task 9.3.1 of 1 day : end date of project is delayd of same duration.
So this task is on critical path.


 
Posted : 30 Mar 2018 17H51
(@vlepetit)
Posts: 15
Active Member
Topic starter
 

ok i understand !!

thank you !


 
Posted : 30 Mar 2018 17H54