Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hello
Here is an example
How is it possible for two linked task to have a relation type "End to start) (The start of second can't start only after the end of the first task) ? and if it is possible, without put fixed date in the "start date validate" field
Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2
It works how you did, but have to "re-calculate" planning.