Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
Hi!
I'm facing a problem. When I assign a resource to activity and want to set hours of assigned work, I will get error at some situations.
If the quantity of hours is less 10,000 hours, it will be good.
But if this quantity is equal or more than 10,000h, I will get error.
Can I change this limit? If yes, how?
Thanks.
This is a restriction that will be changed on V5.3.
Possible values should go up tp 9,999,999.99
If you need to enter assignment or 10,000 hours, you can enter 2 assignments of 5,000 hours for same resource (yes, it's possible 😉 )
NB : IMO 10,000 hours (more than 1,000 days) for same assignment if much too important. :blink:

