Hi
I created a floating milestone which had one predecessor (activity) and one sucessor (activity), right now, I want to change one parameter but I don't know where I can change this property (I don't find it on the documentation), I want to wait 15 d after the beginning of the milestone to start the successor activity, is it possible?
Thanks
In the dependency definition, just set delay = 15 (days)
Thanks Babynus,