[SOLVED] Planned Date

7 Posts
3 Users
0 Reactions
4,112 Views
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 
[#8124]

Dear Friend,Please help me to edit the planned date as it has been changed somehow, now I am not being able to edit it so my Gantt chart is not showing me as per expectation. Please refer attachment, as I need to change the planned date to 11-Feb-2022 instead of 19-Jan-2022. 


 
Posted : 08 Mar 2022 13H53
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

Hello,

the planned end date is calculated by ProjQtOr when you run the calcul of the planning.
if it tells you this date, it means that your activity will end before February 11, 2022 according to the calculation.
 


 
Posted : 11 Mar 2022 12H08
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Thank you, Flow. My question is that how can I edit it manually?


 
Posted : 11 Mar 2022 13H21
Flou
 Flou
(@flou)
Posts: 253
Active Member
 

You can't edit manually the planned end date.
You can change the planning mode on regulare between two date so that your end date matches the planned end date.


 
Posted : 11 Mar 2022 15H59
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Thanks a lot flou for the quick reply, please help me to know which planning mode I should choose to go as you asked?


 
Posted : 11 Mar 2022 16H19
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Use "regular between dates". so that Validated dates will just be used as Planned dates


 
Posted : 14 Mar 2022 16H42
(@chandrashekhar)
Posts: 275
Contributor
Topic starter
 

Hello,
Thank you a lot for this important feature guidance.


 
Posted : 15 Mar 2022 8H35