[SOLVED] Priority on projects and subprojects

2 Posts
2 Users
0 Reactions
3,107 Views
Martin
(@el-wallos)
Posts: 220
Active Member
Topic starter
 
[#2803]

Hi

When you have a project with some subprojects, if I define an important priority (ex: 100) on the main project but priority for subprojects is kept on medium priority (ex: 500), what priority is taken during the calculation planning process? Medium or important?

In fact, I want to know if I need to update the priority only on the main project or on all subprojects too to increase the priority?

Thanks


 
Posted : 08 Dec 2015 18H22
babynus
(@babynus)
Posts: 14953
Main Contributor Admin
 

When you have a project with some subprojects, if I define an important priority (ex: 100) on the main project but priority for subprojects is kept on medium priority (ex: 500), what priority is taken during the calculation planning process? Medium or important?

Priority of subprojects is not changed, kept as medium.

In fact, I want to know if I need to update the priority only on the main project or on all subprojects too to increase the priority?

To all.


 
Posted : 09 Dec 2015 19H48