Hello
please I would like to know ; the existing indice de valeur performance and indicateur de performance en nombre graphs in the report are corresponding to what performance parameters in the project ( delay , charge , .......) as there is no precision about the definition of theses two parameters.
thanks and ragrds
Hi
It is the respect of the estimated work.
Indicator = real work / estimated work (for finished items)
Thank you for your help and assistance, in this case just last question about the second graph , what is the correspondance of indicateur de performance en nombre.
Thank you in advance
It just indicated number of items finished for the corresponding period.
Because a good indicateur for only 1 ticket dies not proove regularity.
Thank you very much for these valuable clarification, do you mean by finished items any activity and ticket with the status done and beyond or any other definition.
Thanks and regards
do you mean by finished items any activity and ticket with the status done
Yes.
In fact exactly I means items with "done" checkbox checked. But as defaut configuration automatically checks it on status doen, yes you're right