[SOLVED] Timesheet : unable to add time

3 Posts
2 Users
0 Reactions
1,725 Views
(@tanguy-daniel)
Posts: 12
Active Member
Topic starter
 
[#8639]

Hello,
Since last upgrade (i applied both 10.1.3 and 10.1.4 one after an other), i 'm unable to add time to timesheet on most of projects.
Furthermore, i 've created a fake project from start with a fake task and i 'm still unable to assign time to this task...
Currently i'm top level user (administrator).
After many tests where i've played with parameters of projects and tasks the problem is still here, icannot understand why, before upgrade it was running well, any information i've missed ? Some parameters to set ?

Need help ! Thank you very much by advance.


 
Posted : 30 Nov 2022 11H51
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Please show some screenshots :
 - the timesheet screen
 - allocation of resource
 


 
Posted : 30 Nov 2022 11H53
(@tanguy-daniel)
Posts: 12
Active Member
Topic starter
 

You give me the hint ! I've searched on others projets, in one of them an other administrator set me as resource  with 100% ratio so i was unavailable for others projets ....
I 've set me off that projet and everything  is working now !
Thanks  a lot !

Topic is closed.


 
Posted : 30 Nov 2022 16H29