The help documentation states that ProjeQtor provides only FS-type dependency.
(Ref: https://en.wikipedia.org/wiki/Dependency_(project_management))
Then it proceeds to cover the other three types (SS, SF, FF).
For SS, it recommends a workaround of adding a milestones for both tasks.
While this is correct, in a normal project, usually there would be a predecessor task that serves the same purpose.
In that case there is no need for a milestone.
I think this needs to be pointed out.
The help should also point out that without a milestone or predecessor task, the activities would typically launch in "ASAP" mode (delayed only the availability of their respective resources), rather than being launched together.
Actual user manual is based on V6.3.
Hope we'll have time to improve it...
No, the limitations are still the same even now.
I suggested extra notes, to clarify the help documentation.
No, the limitations are still the same even now.
Actual user manual is based on V6.3.
There won't be any visible change until we publish new version.