Validated work
 
Notifications
Clear all

Validated work

6 Posts
3 Users
0 Reactions
3,586 Views
(@sanae)
Posts: 2
New Member
Topic starter
 
[#1418]

why is the validates work is not directly calculated by the sum of validated activity work, just as the assigned work?
is there a way to make is calculated automatically ?


 
Posted : 18 Oct 2013 17H27
(@babynus)
Posts: 14952
Member Admin
 

Because in most cases, validated work is defined only on top level (for instance for project, or phase activities). Systematic sum would erase these values...
An evolution is planned to let the choice on sum or not (Ticket #486)


 
Posted : 18 Oct 2013 18H34
Klaus
(@climb4fun)
Posts: 449
Contributor
 

Hi all,

in our perimeter we use validated work as "approved" effort / work for the activities. Hence this value will be entered on a decision, not on a calculation. For us the current implementation is perfect.

In the report "Work synthesis per activity" the summary is not calculated. Here it would be appreciated, when it will be the sum out of all activities related to the project.

Regards,

Klaus


 
Posted : 21 Oct 2013 12H51
(@babynus)
Posts: 14952
Member Admin
 

Hi Klaus,

Note added to ticekt #486
😉


 
Posted : 21 Oct 2013 13H26
(@sanae)
Posts: 2
New Member
Topic starter
 

Still, the program compare the validated work with the assigned work for every activity and sub activity !! so the values should be the same and in this case making both the fields automatically calculated should have been the right thing to do
don't u think ?


 
Posted : 21 Oct 2013 14H50
(@babynus)
Posts: 14952
Member Admin
 

That is why evolution is planned to set it possible...


 
Posted : 21 Oct 2013 16H34