Hello,
It would be good if you could aggregate subtasks' time to the main task, in the "TimeSheet" section.
Best Regards,
Hugo
It fact it won't be possible because resource can also be assigned directly on parent activity, then it's possible to input work on this line, and we won't be able to sum sub-tasks.
And if you do it only on parent that are not assigned, there will ba ambiguity with real work input on this line and then locked.