Hi,
Several countries change official working hours several times a year: summer working hours (fixed start and end dates, account for 1/6 of the whole year working days), ramadan working hours (variable start and end dates (depends on lunar calendar), account for 1/12 of the whole year working days) and the rest of the year working hours (fixed and variable start and end dates, account for 75% of the whole year working days).
Is this already implemented in ProjeQtOr ? Or is there any workaround to implement it ? Or is it on the roadmap ?
Things get complicated, when team is split over two countries or more which don't share the same start and end dates for ramadan, or summer working hours.
TIA.
Is this already implemented in ProjeQtOr ?
no it is not implemented, it is not in the roadmap either and we do not plan to integrate it unless sponsored. You can contact us to get a quote.
One solution could be to use the variation in resource capacity to adapt their FTE depending on the period.