Planning at hour granularity

2 Posts
2 Users
0 Reactions
5,635 Views
 HO
(@sebastien)
Posts: 15
Active Member
Topic starter
 
[#369]

Hi,

On the gantt chart and project planning, do you plan to add hour level?
It would be nice for day to day planning at hour level.

Regards,

Sebastien


 
Posted : 20 Feb 2012 20H09
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

No, it's not planned to have Gannt display at hour level.
Day to day planning at hour level is much to precise: to my own experience, you should not plan tasks > 0,5 day. You'd spend more time planningthan realizing.

To have a look at the day to day planned actitity, each resource can see in the "real work allocation screen" the planned work each day on earch activity.


 
Posted : 21 Feb 2012 20H59