Hi,
I need to follow the following quality indicator on each of my projects:
QI = ((realWork + leftWork) /validatedWork) -1
It calculates the excess percentage of the project.
I do it each week then I save it to draw a graph and see the trend of my projects
Is it possible to add a screen which display the QI for each project with a button (one next to each QI) to save the QI associated to the current date?
Another solution would be to show the QI on project screen whith a button to save the current value with the current date.
The top would be to have a report with a graph showing the evolution of the QI per project. 😎
Thanks
Request registered as ticket #589
Thank you Babynus