[#2176]

Hi,

first let me start by congratulation everyone that has been working on this project ... I just got in touch and looks like a very good solution!!!

Just one thing I'd like to ask, has anyone considered or is developing a time tracker tool to track and directly link to the planned time on the project ?

Thank you.


 
Posted : 27 Jan 2015 1H29
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Have you looked at "Real work allocation" screen.

Or maybe you expect somthing like "Start Work" button (you'll find one on Ticket screen)

If you're thinking about something else, please describe it iso that is can possibly be added in the reoadmap..


 
Posted : 27 Jan 2015 13H58
(@yinyang)
Posts: 3
Active Member
Topic starter
 

Hi Babynus,

The concept would be to have a popup window, or a hover window on a top layer, where a person would be able to choose what tasks/Incident ( or other ) is working on and has a clock counting the time dedicated to the task.

When finish, stops the clock and submits the dedicated effort under the estimated time.

This would enable at the end of the project to have estimated time, real time without forcing the users to submit the worked hours at the end of the tasks or day. IT would be automatically inserted into the system as a person is working on the task.

Does this functionality exists, or do you consider could be considered to the roadmap ?

Thank you.


 
Posted : 28 Jan 2015 0H37
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Hi,

This functionality existys for Tickets : there is a "start work" button.
Try it and tell us if this fits your needs.


 
Posted : 28 Jan 2015 1H57
(@yinyang)
Posts: 3
Active Member
Topic starter
 

Hi Babynus,

unfortunatly no.... one of my objectives for the use of this application was to have a solution not only to plan the work, but also to actually track the effective hours dedicated to it.

But it's implementation would also impact the way the effort is managed in the program, as it accounts only for 1= day work, independent of the hours dedicated/planned for a specific work.

Could it be considered as a possibility, change the tracker of work, from days to hours ?

Thank you.


 
Posted : 21 Mar 2015 21H06
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

You can parameter whever you want to record work in hours rather than day.
Just look at Global parameters.


 
Posted : 21 Mar 2015 23H18