Activity to Milestone copy issue

2 Posts
2 Users
0 Reactions
1,909 Views
(@karl-binet)
Posts: 129
Active Member
Topic starter
 
[#6020]

Hi,

V8.0.3

When i copy an activity to a milestone, the validated cost follows form the activity into the milestone, if i'm right, there should not be any amount in a milestone.

Is this a normal behavior ?

Now, in global planning, we are stuck with milestone that have a validated cost.

How can i get rid of the amount in the validated cost column.

I'm able to delete the amount in the validated cost column from the planningelement table directly into the database, but i don't know if it's the right way to do it or if it will impact somethings else.

If i create a milestone without using the copy feature, there is no amount in global planning.

Can you help,

Regards


 
Posted : 29 May 2019 19H07
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

This is an issue.
Ticket #4030 recorded.
We'll think about fixing wrong existing data while fixing the issue.

(updating data in the table is not a good idea, as change won't be consolidated up to parents)


 
Posted : 30 May 2019 10H49