Forum

Allocation of a res...
 
Notifications
Clear all

Allocation of a resource in manual planning

2 Posts
2 Users
0 Reactions
1,068 Views
(@laurentc)
Posts: 100
Active Member
Topic starter
 
[#8453]

Hi,
When allocate a resource in manual planning the granularity is half day.
However if hours are selected to count the amount of work, the hours count is not coherent with the time line.
Moreover the manual planning granularity should be hours and not half days.
Best regards


 
Posted : 31 Aug 2022 18H05
(@babynus)
Posts: 14952
Member Admin
 

However if hours are selected to count the amount of work, the hours count is not coherent with the time line.

Could you give an exemple ?

Moreover the manual planning granularity should be hours and not half days.

It is for planning, half day granularity should be much enough.
Management in hours (or 1/10 or days for thoose who manage planning in hours) would be technically a real mess, would lead to bad performance on this feature, and we would loose the simplicity for the input. 


 
Posted : 31 Aug 2022 20H31
Share:

Scroll to Top