Burndown chart not following timesheet submissions

5 Posts
2 Users
0 Reactions
1,713 Views
(@squish)
Posts: 5
Active Member
Topic starter
 
[#6542]

When I go to generate a burndown report for a project, it seems to be tracking workload at the time entries are made, instead of following dates that real work has been entered via the timesheet. For example, if on Thursday I enter timesheets for Monday - Wednesday, the burndown chart will show the same amount of work left M-W and then a sharp drop for Thursday.

Can this be toggled to respect the timesheet entries? I don't always have time at the end of a workday to input work for my team, but would like a realistic burndown chart based on when tasks are actually completed.


 
Posted : 04 Mar 2020 18H56
(@babynus)
Posts: 14952
Member Admin
 

Hi,

The behavior is normal : we check changes of left work.
So if you enter several days on the same day, left work is updated only once.

This is difficult to do better as left work may be updated manually so will not always be assigned-real.


 
Posted : 10 Mar 2020 16H31
(@babynus)
Posts: 14952
Member Admin
 

Can this be toggled to respect the timesheet entries? I don't always have time at the end of a workday to input work for my team, but would like a realistic burndown chart based on when tasks are actually completed.

Projeqtor is designed to that you don't have to enter work for the team. Team members do.
And best practice is to enter work every day...


 
Posted : 10 Mar 2020 16H32
(@squish)
Posts: 5
Active Member
Topic starter
 

In our specific use case it is not feasible for team members to enter in their own times. This is a manufacturing setting where most do not have anything above basic computer skills, and we have multiple contracts that their resource pool is assigned to. They would be potentially choosing between over 300 different activities to enter their times.

Are the left work changes tracked using the host time or client-side time? In other words, if I change my computer's date to match when the work was actually done, will Left Work be updated using the "fake" time, or using the server-side time?


 
Posted : 10 Mar 2020 16H51
(@babynus)
Posts: 14952
Member Admin
 

Are the left work changes tracked using the host time or client-side time? In other words, if I change my computer's date to match when the work was actually done, will Left Work be updated using the "fake" time, or using the server-side time?

Server Time.
So no.


 
Posted : 10 Mar 2020 18H47